Specialty Reports, ARRA, HUD, Transit - New Hire Report

Modified on Mon, 16 Dec, 2024 at 5:41 AM

Report Description: this report will show hired employees based on “new hire” dates defined during project implementation. It contains the following information:

  • Project name
  • Report date range
  • Project code
  • Contractor name
  • Employee name
  • Employee city
  • Employee craft
  • Employee hire date
  • Employee hours worked
  • Amount paid to employee to date
  • Total number hired by contractor
  • New hire hours worked
  • New hire amount paid
  • Total workers on job
  • Total hours worked
  • Total amount paid
  • Percent of number of new hires
  • Totals for all categories


Preconditions: under Set Up > Add/Edit Projects an estimated start date must be entered for this report to run. If the new hire days (backend setting) is set to the default of 90 days, any employee with a hire date within the 90 days prior to the start date of the project, and then any time after the start date, will be considered a new hire on the project.  

This default setting of 90 days is a backend setting that can be changed by your LCP Customer Success Manager.  It can also be overridden on a per-project basis in the Project Set up tab.


Parameters:


Report Sample:

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article